Omm is 50% as efficient as Shiv. Shanti is 25% less efficient than Omm. If Shiv alone can complete the work in 60 days, In how many days can they together complete the work?

A. 36

B. 32

C. 24

D. 12

Correct Option is B

Explanation:

Omm is 50% as efficient as Shiv. Shanti is 25% less efficient than Omm.

Let the Efficiency of Shiv = 8 

( Note:8 = 2*4 which are the denominator of fractions)

Efficiency of Omm = 4

Efficiency of Shanti = 3

8 * 60 = (8 + 4 + 3) * x

x = 32

 