Aryan can complete a piece of work in 9 days. Arav is 25% less efficient than Arav. In how many days can Arav complete the work alone?

A. 24

B. 18

C. 36

D. 12

Correct Option is D

Explanation:

Aryan can complete a piece of work in 9 days. Arav is 25% less efficient than Arav

Let the efficiency of Aryan = 4

Efficiency of Arav = 3

4 * 9 = 3 * x

x = 12