Q. |
Karan can complete a piece of work in 30 days. Rajan is 50% more efficient than Karan. In how many days can Rajan complete the work? |
A. 60 |
|
B. 15 |
|
C. 20 |
|
D. 10 |
Karan can complete a piece of work in 30 days. Rajan is 50% more efficient than Karan.
Let the efficiency of Karan = 2
Efficiency of Rajan = 3
We know, E1D1 = E2D2 (Read the concepts and watch the video of this concept)
2 × 30 = 3 × x
x = 20