A and B can complete a piece of work in 10 and 20 days respectively. If they work in alternate days, starting with A, in how many days will the work be completed?

A. 10

B. 11

C. 12

D. 13

Correct Option is D

Explanation:

Let the total work  to be completed = 20 units (LCM of 10 & 20)

On the first day, A can do 2 units of work

On the second day, B can do 1 unit of work

3 units of work will be completed in 2 days

18 units of work will be completed in 12 days.

Next day A will complete 2 units.

Hence total number of days = 12 + 1= 13 days