Ram and Shyam can complete a piece of work in 10 and 15 days respectively. If they work in alternate days, starting with Ram, in how many days will the work be completed? 

A. 6

B. 10

C. 12

D. 16

Correct Option is C

Explanation:

Let the total work  to be completed = 30 units (LCM of 10 & 15)

On the first day, Ram can do 3 units of work

On the second day, Shyam can do 2 units of work

5 units of work will be completed in 2 days

30 units of work will be completed in 12 days.